How long does it take to build a CRM? In our plan, a first version that your sales team works in every day takes ten weeks, counted from the first call. A full system that holds most of the business takes months. Setting up a boxed product such as Salesforce or HubSpot is a different job, and one we do not take on.

Ten weeks is a plan, not a date promised before anyone has seen your process. The scope agreed in the first week decides it, and a change to that scope is quoted before the work starts.

Below is how those weeks run when we build a custom CRM, with what you can open and check at the end of each step. After the plan come the things that stretch the calendar, what deliberately waits for later, and what to have ready before week one.

How long does it take to build a CRM? Three different answers

The question covers three different jobs, and each one runs on its own calendar.

A first version your team works in. Ten weeks in our plan, counted from the first call until your sales team uses the system every day. It covers your stages and roles, your pricing rules, your history and one integration, and you can stop after any stage.

A full system. How long does it take to develop a CRM that holds most of the business? Months, not weeks: for systems in general, our answer is four to eight months, depending on how much of the business the system has to hold. Anyone promising a full platform in six weeks is describing a demo.

Our largest running system took eight months: an operations platform with 81 data models and 2,053 automated checks, which a whole company works in. It is not a CRM, and none of our published cases is one, so read the ten weeks as our plan for a first version rather than a record of earlier CRM projects.

Setting up a boxed CRM. If what you need is to set up a CRM you are buying, such as Salesforce, HubSpot, amoCRM or Bitrix24, that is work for the product’s own integrators, and we do not take it on. So this article says nothing about how long such a setup takes.

The ten weeks of a first version, week by week

Our plan has six steps over the ten weeks. Each ends with something you can open and check, and each needs something from you; that second part decides whether the step ends on time.

  • Week 1: your process on paper. We sit with your sales lead and draw how deals really move and how prices are worked out, and we agree which system gets connected and what the import will look like. The week ends when your sales lead says the drawing is right, which can take one meeting or several.
  • Weeks 2–3: deals and permissions. The basic records and who may see and change them. By the end of week three the system runs at a real address, and your team can click through it instead of reading about it.
  • Weeks 4–5: the part that made you leave. Your pricing and approval rules, checked against real deals you bring, including the awkward ones. These weeks end on time if those deals arrive in week four rather than in week five.
  • Weeks 6–7: your history moves in. The data comes across with every doubtful record listed for you to decide. The step ends when someone on your side has gone through that list and signed it off.
  • Week 8: one integration. The one system chosen in week one gets connected. Part of its pace belongs to the company behind that system.
  • Weeks 9–10: real use, then handover. Your team works in the system for a week while we fix what they find, and then it moves across to you.

What each step hands over is listed on the CRM service page linked above; this article is about the calendar.

The order matters as much as the length. Something you can use exists from week three onwards, and every later step adds to it rather than saving a big reveal for week ten.

Why the unusual part of a CRM goes first

Contacts, companies and lists are the predictable parts of a CRM: they take the time they take. The part that sent you looking for something new is where the surprises are, so it goes first, while a surprise can still be absorbed.

Projects that start the other way round tend to stall. A team copies the product it is leaving, screen by screen, and the money runs out before the work reaches the reason they left. Our plan begins with that reason and fills in the familiar parts afterwards.

On the calendar, that is why weeks four and five go to pricing, quoting and approvals, before your history moves in and before any integration is wired. If a pricing rule turns out to be harder than anyone thought, you find out in week five, with half the plan still ahead.

Which features make the first version and which wait is settled in week one, together with you, rather than fixed before anyone has seen your process.

What stretches the ten-week calendar

The plan assumes that the scope agreed in week one stays put and that answers arrive when the work needs them. Five things stretch it, and most of them sit on your side of the table.

Your history. Years of deals and contacts do not simply copy across: every source disagrees with the others somewhere, and someone has to settle each disagreement. That work has its own two weeks, six and seven, and needs people from your side. The more places your history lives in, and the more they disagree, the more there is to settle.

Integrations. Connecting another system means working to that system’s documentation and its company’s timetable. The first version carries one, chosen in week one, so a single outside company’s pace sits inside your ten weeks. Every extra integration pulled forward brings another schedule that nobody on the project controls.

Your time and decisions. The plan needs someone on your side for a couple of hours a week, and when an answer is late, the step waiting for it is late too. A sales process your own team disagrees about stops the calendar in week one, and no amount of development speeds that up.

Rules that live only in heads. A discount nobody wrote down, an approval that happens only because one person remembers it: rules like these tend to surface late. One that appears after week five reopens work already built and tested, so it counts as a change of scope and is quoted before the work starts.

Duplicates only you can decide. When the same company appears three times with different details, only your side knows which version is true. The import step closes only when someone of yours has checked every doubtful record and signed the list off.

Time and money share these causes. If you have already read about custom CRM cost, the list will look familiar; here it is told as a calendar rather than a bill.

What deliberately waits for phase two

A first version fits into ten weeks partly because of what it leaves out on purpose: reports beyond the basic ones, every integration after the first, and sales forecasts, because the data has to be trustworthy first; marketing automation is better bought than built. None of it is forgotten, and none of it uses up any of the ten weeks; the service page sets out what the first version leaves out, and why.

One item can move forward. A mobile app for people who work away from a desk usually follows once the team has used the system for a while, but it joins the first version, priced separately, when the field is where your deals happen. It comes from the same team either way, because mobile apps are our specialisation.

If the budget is smaller than the list, the list gets shorter; the unusual part keeps its place at the front.

What to have ready before week one

Week one settles your stages, who may move what, the pricing rules, the first integration and the shape of the import. It goes further when you arrive with these already on paper:

  • The pipeline as it runs today: the stages a deal really passes through, and who may move it from one to the next.
  • The pricing rules as arithmetic, including the exceptions that someone usually settles by phone.
  • The one system you cannot work without, whether accounting, telephony or mail.
  • The size and state of your history: where it lives, how much of it there is, and how far the sources disagree.
  • Two names: someone who knows the process and has a couple of hours a week for questions, and the person who decides between duplicate records.

A rough page for each is enough. Turning them into a diagram your sales lead agrees with is what the first week is for.

What happens after week ten

Weeks nine and ten begin with a week of real use: your team works in the system while we are still there to fix what annoys them. After that the release process, the written instructions and the accounts move to you, and one of your developers deploys the system once while we watch.

You own the work long before week ten: the code and the servers sit in your accounts from the start, and you can stop after any stage and keep what is built. Those terms, and the price, are on the custom CRM page.

One thing no plan changes: a CRM does not sell for you. It takes friction out of the work and shows what is really happening; the selling is still your team’s.

Your next step

How long does it take to build a CRM for your company, rather than for companies in general? Send a page about how you sell, and a basic estimate comes back within 12 hours, with the scope it covers and the list of things we assumed.

If a boxed CRM would do the job, we will say so on the first call. Most companies should buy one, and it is better to hear that before week one than after it.